Add Time for Work Order Work Performed

Add Time for Work Order Work Performed

1) Open an employee Timesheet record

2) On the toolbar, select Service Request

3) Click + Add

4) Select Service Request Number from drop down list

5) Enter hours and Pay Type

6) Click the White Checkmark 

    • Related Articles

    • Add, Modify, & Delete Resources on a Work Order

      Resources on a work order are employees, equipment, or contractors. These are added to a work order to track time and cost.   Add a Resource to a Work Order Click + Add on the Resource zone.  Select Employee, Equipment, or Contractor at the top. ...
    • Work Order Compliance - Work Order

      Compliance notes in NEXGEN allow users to note items relevant to compliance on a work order record, such as LOTO assets or outages, all in one spot. This is useful for noting whether a work order has the potential to impact things such as safety or ...
    • Create a New Work Order - Work Order

      Work Orders are records that track maintenance on one or more assets. When creating a work order, you want to fill out as much information as necessary in the Work Order Information zone to give everyone the info they need to complete the work. Work ...
    • Create a Work Order from a Template - Work Order

      Creating work order from a template saves the end user time because the user has less fields to fill in at the time of creating a work order. Work Order templates can be pre-loaded with checklists, notes, assets, resources, and more. Work Order ...
    • Quick Add - Work Order

      Using the Quick Add filters, users can create work orders according to certain filters (Department, Type, Main Task, Priority, etc.). Filters can be saved to create a work order with the same information the next time. Filters are saved per user ...